A practical guide to building and editing timelines
Project Timeline is chart-first: most work happens on the timeline itself. The side panels and data table back up the chart rather than replace it.
1. Getting started
Add events with the Task, Milestone, Decision and Notice buttons after Add: in the data table's heading, or use a template from the side panel.
Title — click the chart title to rename the project.
Undo ↶ / Redo ↷ in the toolbar (or Ctrl+Z / Ctrl+Y) reverse edits.
Work is auto-saved in this browser. Sign in to sync projects to your account.
2. Editing on the chart
Tasks (bars)
Move — drag the bar left/right.
Resize — drag the left or right edge handles.
Progress — drag the progress handle on the bar.
Delay — use the delay handle (or set delay in the table/modal).
Details — double-click a bar (or use the table) for name, links, resources, predecessors, notes. Dependencies and Resources each fold away under their heading — the number beside it says how many are ticked — and stay folded for the next item. Drag the bar under a list to make it taller or shorter; double-click the bar to reset it. A–Z beside Resources sorts that list by name, with the people on the item kept at the top.
Delete — hover a bar and press Delete / Backspace (not while typing in a field).
Overlaps — in the timeline view, items that overlap in a group stack upward so none is hidden. Tick Stay in place when overlapping in an item's details to keep it on its line instead.
Milestones, decisions & notices
Drag to move; double-click for details.
Notices carry detail text and do not take predecessors like tasks do.
Dependencies (arrows)
Drag from a connection circle on a bar to another task to set a predecessor.
With Start-date dependence on (Options), starts can follow predecessors automatically.
Earliest begin — set in an item's details, or from its start date in the table, it is a hard limit: the item never starts before that date, whether or not it follows its predecessors.
Critical path highlights the longest chain of dependent work.
3. Zoom, pan & fit
Zoom slider — changes day width. Zoom in until a single week fills the window.
Weeks (wk) — set how many whole weeks fit in the viewport (arrow keys step by 1).
Fit to Tasks — sets the view range around your work.
Fit to Window — scales the chart so the full span fits the pane width. Group and resource name columns stay pinned on the left while zoomed. The button only shows while the chart does not already fit the window.
View range (📅) — pin From/To dates; clear them to auto-fit again.
Day dates — with 7 weeks or fewer in view, every column is dated under the chart; wider than that, there is one date per week.
Week numbers — click them on the chart to hide them; click the same strip again to bring them back.
Drag empty chart space to pan when the plot is wider than the window. Scroll the resource chart to pan both panes together.
4. Groups & categories
Groups (left column / chart labels) gather tasks vertically. Drag group labels to reorder; double-click to rename; ✕ removes an empty group.
Double-click the italic groups header in the chart gutter to rename that label.
Categories (phases) color the bars. Manage names and colors under Graphics → Category colors, or click a legend swatch on the chart.
5. Resources
Add resources in the left panel or from a task’s Resource(s) field.
Assign people (or teams) to tasks with a % allocation. Use Variable for day-by-day schedules.
The heat map under the timeline shows utilisation. Colors go from the Utilization 0% to 100% graphics settings. The same gradient tints Resource(s) chips in the data table (average % if several resources).
Click a heat cell to edit that day’s allocation, mark the day off, or add a longer absence to that person’s days-off list. A day can be a half day off, which counts half that person's work and cost; in the days-off list, ½ makes every day in a range a half day.
Team resources (sign-in) are a shared list you can push from a project resource (🤝+) or pull into the current project. In a team, it is the team's list, the same for everyone in it. Sort it by name or day rate from its headings, and drag the bar under it to make it taller or shorter.
Costs
Give a resource a day rate in the Resources panel and tick Show resource costs beside + Add resource. The summary column then shows each group's cost, and the resource chart each person's. With the summary column open, the Costs box beside Summary under the chart does the same.
Actual & forecast appears under Show resource costs once it is on. It adds two columns after Cost: what is already spent, up to and including today, and what is still to come. The two always add up to Cost.
With a baseline shown, Cost Δ compares each group's cost with the baseline's — red where it now costs more, green where it costs less.
6. Calendar & non-working days
Toggle weekends, pick a holiday region, and choose date format under Options → Calendar.
Add custom non-working ranges (e.g. site shutdowns).
Break view (Pro) leaves date ranges of your choosing out of the chart. Tick it, then add each range in the box that opens under it. A break mark shows where each one was — hover it for its name and dates. Dates and scheduling don't change.
Saved calendars store weekend/holiday/format/custom days for reuse (synced when signed in).
Shift all dates moves every task by N working days.
7. Graphics & colors
Adjust corner radii, font scale, day/week lines, background, delay/arrow/today colors, and utilisation gradient.
Eye icons hide/show some chart elements without losing color settings.
Reset graphics restores the default graphics options (bottom of the Graphics panel).
Category palettes (built-in or custom) recolor phases; custom packs can include graphics settings too.
Custom watermark (Pro) — in Graphics, switch on Custom watermark, type your text and pick its color. It sits where the free version shows project-timeline.com, on screen and in every export. Set its size, and move it to another corner or the centre. Click the watermark on the chart to edit it right there, or to hide it.
Company logo (Pro) — in Account, Choose image… puts your company's logo at the top left in place of the Project Timeline logo and name. It is kept with your account, so it follows you to other computers.
Palettes in every colour box — pick a ready-made palette or one of your own from Palette at the bottom of the box, then click a colour to use it. On your own palettes, ✎ renames it, + adds the colour at the top of the box and × on a colour removes it; + on a ready-made palette starts your own copy. To delete one of your own palettes, click 🗑 and then Delete?. Pick + New palette at the end of the list to start one of your own.
8. Data table
Edit names, types, groups, categories, dates, delay, progress, and resources in bulk.
Click column headers to sort; drag headers to reorder columns; drag edges to resize.
Start dates open a popup for the date and an optional earliest-begin constraint. With Earliest begin ticked, the date can move later but not earlier.
Hide it with Hide beside Fit — it appears when you point at the table — or by unticking Data table in Options; D brings it back. Or drag its ⠿ to put it — and the Team Project View — above or below the four panels.
9. Saving, export & cloud
Local auto-save — state is kept in browser storage.
Import opens a project file (.json), or reads tasks from a .csv or a GanttProject file (.gan). From a .gan, each top-level summary task becomes a group, and dates, progress, notes, people and finish-to-start links come across. Export saves the full project as .json, and Export .csv the task list. With Pro, Export all in My Projects saves every project as its own .json file, together in one .zip. With Replace existing tasks on import ticked, the groups, categories and people only the old tasks used go too; Undo brings them back.
SVG / PNG / PDF — export the chart from the toolbar.
Sign in — multi-project cloud storage, version history, team resources, and synced palettes/calendars/templates.
Folders — in My Projects, New folder groups your projects. Drag a project under a folder to file it, click a folder to fold it, and drag a folder by its ⠿ to reorder.
Versions and files live in the Versions, files & templates panel: History and Baselines, Import/Export and Templates. Templates load example projects (replace the current one) or your own saved templates.
History & baselines — saved versions are listed under
History and Baselines in the Versions, files & templates panel.
Save a version saves straight away; click a version's name to rename it, and use the star to
pin it so it is never trimmed away — pinned versions are the basis for
baselines.
Baselines on the chart — while a baseline is shown, its late, early and on-plan colors join the chart legend after a divider, and the summary gains BL Δ (days) and, with costs on, Cost Δ.
Sharing
Open My Projects and use a project's people button to invite someone by email, or to create a public read-only link.
On a project someone shared with you, the same button shows who else is on it.
As the owner you can tick Let people on this project invite others, or use Transfer ownership to hand the project to someone who has signed in at least once — you stay on it as a member.
Teams
Create a team — press + Team in the Team resources panel. Creating a team needs Pro, and your own list of people becomes the team's list.
Invite — admins invite colleagues by email from the Team window. They see the invite the next time they sign in with that address; joining is free.
One list for everyone — everyone in the team uses the same list of people. Admins can change it, and can tick Members can edit the team list to let everyone change it.
Share a project with the team — tick Share with my team in a project's share window. It then shows, read only, in the Team Project View of everyone in the team who has Pro. To let someone edit it, invite them to the project as well.
Admins can make others admins, remove people, and rename or delete the team. A team always keeps at least one admin, and each person can be in one team.
Team Project View
A Pro view of your whole account: turn on Team project view in Options. Projects shows every saved project as one bar — first start to last finish, filled to its progress, with its milestones — and Shared resources shows who is booked across all of them, with anyone over 100% outlined.
The people and projects pickers filter both sections. Press ⟳ to read your projects again after changing them. A–Z in the people or projects picker sorts that section by name; drag a project or a person by its ⠿ to put them in your own order. Point at the view for Hide; turn Team project view back on in Options to bring it back.
Team projects — in a team, the view also shows every project shared with the team, with its owner's name after the title.
10. Gantt view
The Gantt view button in the toolbar switches between the compact timeline
(several items share a row) and a traditional chart where every task, milestone,
decision and notice gets its own row. The button always names the view you would
switch to, so it reads “Timeline view” while you are in Gantt.
Groups/categories are not used here — the left gutter simply lists item names,
ordered by start date. Group reordering and the add-group button are hidden.
Dragging a bar sideways changes its dates, and up or down moves it to another group — both in one drag if you like. A task that follows its predecessors keeps its start date.
Row height — the box beside the toggle sets the height of every row.
Dragging the handle at the bottom of the chart overrides it and updates the box.
Scrolling — past 750 px tall the chart area scrolls vertically instead of
growing without limit. The date header stays put.
Indent & group — the small arrow to the left of an item indents it by one
level under the item above. The parent then shows a caret you can click to
collapse the group; collapsed parents are drawn with a thick outline and
span the full date range of their children, and their title gains
(group).
Dependencies pointing into or out of a collapsed group are redrawn to the folded parent,
so no link disappears when you collapse.
11. AI assistant
The ✨ panel at the bottom-left edits your plan from plain English, and answers questions
about it. Signing in is required, and each exchange appears in a scrollable
conversation above the input box.
Editing — “Shift PCB Layout 3 days later”, “Add resource QA team”,
“Make Design category blue”, “Assign the QA team at 60%”.
Watermark (Pro) — “Set the watermark to Acme Corp, bottom left, at 40%” changes the custom watermark's text, colour, opacity, size and position, or turns it off.
Asking — “When does this project finish?”, “Who is over-allocated?”,
“What is on the critical path?” Questions change nothing.
The whole batch is one undo step (Ctrl+Z).
Anything that deletes data is previewed first with the affected items flagged,
and only applied when you press Apply changes.
If a shift appears to do nothing, the reply will say so — a task set to follow its
predecessor is put back by auto-schedule. Shift the predecessor instead, or untick
Start-date dependence.
Your API key never reaches the browser; requests go through a server-side function.
12. Free & Pro
Everything on this page works on the free plan. Pro raises the limits — see the
Pro page for the full comparison.
Free — 4 groups, 3 resources, 2 saved projects, the first 10 tasks in the
data table, 3 saved versions per project, and 2 AI requests a day.
Pro — up to 20 groups, 50 resources, 50 saved projects, 100 table rows,
50 AI requests a day, 15 saved versions per project, a removable watermark or one of your own, baselines,
the Team Project View, running a team, Export all, and saved templates, calendars, color palettes and a team resource list.
Nothing is deleted if a subscription lapses; saved items stay readable, you just
cannot add new ones.
13. Tips & shortcuts
Hover ⓘ icons in side panels for short explanations without permanent help text.
Ctrl+Z / Ctrl+Y — undo / redo
Delete — remove the hovered chart item
T — fit the view range to your tasks (not while typing in a field)
S — show or hide the summary column
P — collapse or expand the four settings panels
R — show or hide the resource chart (opens it if it is folded)
D — collapse or expand the data table, or bring it back when it is hidden
G — switch between timeline and Gantt view
C — show or hide the critical path
W — fit the timeline to the window width
E — export the chart as a PNG image
A — open or close Timeline AI
In Options, a switch's key is the letter in bold in its name — Resources chart is R — or the small key shown after it.
Wheel over the chart — zoom behaviour depends on focus; use the zoom controls for precise week counts
If labels look misaligned after zooming, press Fit to Window again (it resets horizontal scroll)
Collapse side panels and the table for more chart space
Click the heading of the data table, the resource chart or the Team Project View to fold it